Lessons Learned & Post-Implementation Review
Check whether the change delivered what it promised, and capture what to repeat and what to avoid next time.
Where it fitsStage 7 of 7 · Sustain: Did it work, and will it last?
What it is
A review kit for the end of a phase or programme. The guide sets out when to hold reviews, the four questions to ask and how to run a blame-free session. The review page compares objectives, scope, cost and benefits with what actually happened. The lessons log turns each lesson into an action with an owner and a date.
Why use it
Lessons-learned documents are often written and never read again. The value lies in the actions that follow. A structured review against the business case also tells the board whether the investment paid off.
How to use it
- Hold short lessons reviews at each gate and at go-live, while the team is still together.
- Three to six months after go-live, compare planned and actual scope, time, cost and benefits.
- Gather input anonymously first, then discuss it with a neutral facilitator.
- Agree the top three lessons, not thirty, and find the root cause of each.
- Turn each lesson into an action with an owner outside the programme and a date.
When it helps
- At each phase gate or go-live
- Three to six months after a programme closes
- After a project that went badly, to learn without blame
- Before starting a similar programme
What is inside
- A guide to timing, the four questions and running a good session
- A post-implementation review against the original promise
- A lessons log that turns lessons into owned actions
Worked example
The post-implementation review against the original business case.
| Time | Went live four weeks late, because of the core system interface. Partly met. |
|---|---|
| Cost | £1.32m against £1.2m, including £80k for open banking. Partly met. |
| Benefits | 8 days to a decision against a target of 7. 1.2 hours of checking against 1. Mostly met. |
| Keep doing | Testing AI on real past cases before committing, and involving underwriters and the staff forum in design. |
| Do differently | Test the full variety of documents before choosing a supplier. Agree system interfaces before the business case. |
What happened next. Procurement now asks every AI supplier for a test on the lender's own documents. The next diagnosis has started, on personalised savings offers.
Preview
Questions
When should a post-implementation review happen?
Three to six months after go-live, when the change has settled and early benefits can be measured. Hold shorter lessons reviews at each phase gate and at go-live too.
How do you make lessons learned actually change anything?
Agree the top three lessons rather than thirty, turn each one into an action with an owner and a date, and send it to the people who can make it happen, such as the PMO, HR or procurement.
Rate and review
How useful was this template?
Your rating and comments help me improve the template and decide what to build next. It takes less than a minute.
Thank you.
Your feedback has been sent. If you have got another minute, share the template with someone who'd find it useful.