Good programme governance makes decisions faster

Most programme governance is designed to review. The useful kind is designed to decide, and makes it obvious who decides what.

Ask people on a large change programme what governance means and many will describe meetings: a weekly project board, a monthly steering committee, a design authority, a risk forum. Ask what decisions each of those meetings made last month and the answers get vaguer.

Governance tends to grow by addition. Each new risk or escalation adds a forum, a template or a sign-off, and nothing is ever taken away. Before long a simple decision takes weeks, because it has to pass through several groups and none of them feels it owns the call.

If a decision needs three meetings, it does not have an owner. It has an audience.

Start from the decisions

Better governance starts with a list of the decisions the programme will need to make. The meetings come later. Scope changes, budget releases, design choices, go-live calls, supplier problems. For each type of decision, agree who is accountable for making it, who must be consulted first and who simply needs to be told afterwards.

That is what a RACI is for, although it is often filled in once and then filed. A few rules keep it useful:

  • One accountable person per decision. A committee or two directors will not do. If accountability is shared, nobody holds it.
  • Fewer people consulted than you think. Every name in the “consulted” column adds time. Keep it to the people whose input could change the outcome.
  • Delegate by threshold. Set clear limits, for example on spend or schedule impact, below which the programme decides without escalating. Most decisions should never reach the steering committee.

Then design the meetings

Once decision rights are clear, the meetings almost design themselves. Each forum exists to make a defined set of decisions, and its agenda is built around them. A meeting with no decisions to make that month can be cancelled without anyone missing it.

The same logic applies to the paperwork. A RAID log is worth keeping only if every risk and issue has an owner and a date for action, and if it is used to start conversations. Too many logs just record that the conversation never happened.

Try thisPick three decisions your programme made in the last month. For each one, trace how long it took from first being raised to being made, and how much of that time was spent waiting for a meeting. If waiting beats working, your governance is slowing you down.

Take things away

When governance is slow, the instinct is to add something: a new escalation route, a fast-track forum, another dashboard. The better fix is usually subtraction. Merge forums that make overlapping decisions, raise the thresholds for escalation and give named people the authority to decide. I have never seen a programme fail for lack of meetings. I have seen plenty struggle because nobody in those meetings felt able to say yes.

Try it yourself · free templateRACI & Governance PackMake it clear who decides, who does the work and how issues travel, before the first argument about it.Download free →

If this was useful, please pass it on.

Mayank Paliwal
Mayank PaliwalFounder, InflexionIQ

Mayank works on business transformation, strategy and operating model design. He is an independent consultant and founder of InflexionIQ, previously at Deloitte, with a master's in Strategy & Innovation from Saïd Business School, University of Oxford.

The Inflexion Note

No schedule. Just a note when I learn something worth your time.

One idea, one free resource and one thing to try. If I have nothing useful to say, you will not hear from me. Unsubscribe with one click.

I will only use your email to send the Note.